Horizontal Re-bar
Horizontal steel reinforcing bar (re-bar) must be installed
as the wall assembly is erected. The re-bar is placed
in the tandem re-bar saddles provided on the center
of each wall-tie every 12-inches on center, although,
it may only be necessary to install horizontal re-bar
every second or third course. These dual re-bar saddles
will accept both ½ and 5/8-inch re-bar. All overlapping
splices, including those at corners, should overlap
36 bar diameters and should be tied with wire. It will
also be important to plan the placement of re-bar to
correspond with other elements of the wall assembly.
It is a good idea to check the details of window and
door openings, lintels, and other wall features to determine
the required steel reinforcing. It is much easier to
place re-bar as the wall assembly is being erected than
it is after. See: Vertical Re-bar.
Engineering and architectural specifications
and drawings will determine the size, grade, and the
position of the steel reinforcing bars. The placement
and design of steel reinforcing shall be in accordance
with local standards and regulations, and in conformance
with ACI 318-95 Building Code Regulations for Structural
Concrete.(back to top)
Vertical Re-bar
Vertical steel reinforcing (re-bar) dowels should be
placed in the footer at regular intervals. These dowels
should correspond with the design of the re-bar required
in the wall. This will provide solid attachment to the
footing. See: Footings.
The vertical re-bar is most easily put in place full
length after the wall assembly is erected and prior
to concrete placement. Several methods can be used to
hold vertical re-bar in place. First, attach an open
wire loop at the top of the dowels large enough so that
the vertical re-bar can be passed through and held in
place at the bottom once the wall assembly in completed.
Second, a two-inch length of PVC pipe (a ring) can be
slipped over the dowel and serve the same purpose as
the wire loop. Both the wire loop and the PVC ring need
to be sized correctly so the vertical re-bar is held
reasonably tight to the vertical dowel protruding from
the footer. Third, various market-ready re-bar positioners
are available, and fourth, the vertical re-bar can be
bushed into the correct location as the first lift of
concrete as it is being pumped in place. All of these
methods allow for full-length re-bar to be used. A fifth
way is that the vertical re-bar can be installed in
two or more pieces with joints that overlap 36 times
the bar diameter and tied with wire. With this method
the vertical bar can be tied to the horizontal re-bar
with wire, and the forms will be installed by slipping
them over the vertical re-bar. See: Vertical Re-bar
It may be necessary for workers to hold and/or move
the vertical re-bar into place during concrete placement.
If this is done, care should be taken to insure that
the re-bar is maneuvered into proper position as the
concrete is being placed. This will need to be done
during all lifts of the concrete pour. See: Concrete
Placement.
If vertical re-bar is not to extend and connect to
a wall of an additional story above, it should be cut
to a length 1 or 2-inches shorter than the wall height.
If the vertical re-bar is to extend and connect to a
wall of an additional story above, it should be cut
to a length so that it will overlap 36 bar diameters
with the vertical re-bar that will be installed above.
Or, short pieces of re-bar can be placed in the fresh
concrete at the top of the wall, that are long enough
to protrude into and connect to the wall that will be
built above.
The vertical re-bar can be tied in place or it can
be held in place when concrete is being pumped into
the forms. It is important to know that for above grade
walls the re-bar should be held in the center of the
wall cavity. For below grade basement foundations where
there is lateral load (pressure) against the wall the
vertical re-bar is best held off center on the tension
side (basement side) of the wall with a minimum of 1-inch
concrete cover. It is important to plan the placement
of re-bar to correspond with other elements of the wall
assembly and to check the details of window and door
openings, lintels, and other wall features to determine
the required steel reinforcing. See: Horizontal Re-bar.
Engineering and architectural
specifications and drawings will determine the size,
grade, and the position of the steel reinforcing bars.
The placement and design of steel reinforcing shall
be in accordance with local standards and regulations,
and in conformance with ACI 318-95 Building Code Regulations
for Structural Concrete.(back to top)
Intersecting Walls (T-walls)
To connect intersecting walls it will be necessary
for the concrete and steel re-bar of both walls to be
linked together. To accommodate for the re-bar and the
flow of concrete, sections of the foam panel on one
side of the adjoining wall will need to be removed.
To form a non-fire rated T-wall, remove sections of
foam located above and below the wall-ties and between
the flanges of the studs. It is important to avoid cutting
the stud wall-tie brackets, whenever possible.
When the cutting wall-ties is unavoidable, such as
when forming a solid monolithic fire rated T-wall, or
when the entire side of the adjoining wall needs to
be removed, it will be necessary to reinforce the intersecting
area in order to withstand the pressures created during
concrete placement. Reinforcing is usually accomplished
by supporting the area with pieces of wood attached
with course thread screws, and replacing the cut plastic
wall-tie brackets with wall ties made of wire to hold
both sides of the wall assembly together. See: External
Bracing.(back to top)
External Bracing
Bracing is not required under normal circumstances
for the pre-molded corner forms. This is especially
true if the horizontal joints are glued and the correct
concrete slump is being used during concrete placement.
Many installation contractors choose to use vertical
plumb boards at the corners to insure that the installation
of the wall assembly is plumb and the building is square.
External corner bracing is required when corners are
made from straight forms miter cut to form a corner.
In this case the corners will need to be reinforced
and braced to accommodate the pressures of concrete
during concrete placement. To reinforce mitered corners,
the cut joints should be glued with foam-compatible
contact adhesive or minimum expanding foam adhesive
and taped. The corner will need to have temporary wood
or metal supports applied vertically and tied together
through the wall with wall ties made by using tie wire
and braced with kickers from two directions.
The construction of intersecting walls (T-walls), gable
end walls, and other complicated or difficult areas
where the integrity of the forms has been compromised,
will also require external bracing. Care should always
be taken when placing concrete in these areas, lowering
the risk of form separation, wall deformity, budges,
and blowouts. See: Intersecting Walls, Cut Forms and
Splices, Bulkheads, Gluing Forms, and Window and Door
Openings. (back to top)
Window and Door Openings
Window and door frames (bucks) are installed by placing
a vinyl or wood frame that has the same inside dimensions
as the required rough opening (RO) size as supplied
by the window and door manufacturer.
Use pressure treated 2 x 12 dimensional lumber to construct
the top and sides of the frame, but use two 2 x 4's
on the bottom leaving a space between them for concrete
to be placed under window or door openings. It may be
advisable for this space to be filled with a third piece
of 2 x 4, to be used for attaching finished materials,
once the concrete has filled the cavity under the frame.
The frame is left in place after the concrete is cured
providing a fastening surface for the installation of
the windows, doors, and finish trim.
Attach temporary 1 x 4 wood flanges on all edges of
the wood frame to position and hold the form in alignment
with the wall. Additionally, temporary vertical, horizontal,
diagonal and/or cross bracing will need to be installed
to reinforce the frame to prevent the weight of the
concrete from pushing in, down, and up against the frame
causing it to move and/or change shape. It should be
noted that ready-mixed concrete weighs approximately
4000 lbs. per cubic yard and bracing should be built
accordingly.
Metal fasteners (nails, screws, or bolts) should be
installed into the frame (top, sides, and bottom) prior
to the placement of concrete so they protrude into the
wall cavity securely anchoring the wood frame in-place
once the concrete is cured.
Commercially available preformed plastic and vinyl
frames are installed similarly and provide the same
utility. Follow the instructions for installing vinyl
frames as provided by the manufacturer. Manufacturers
of these products are: ICF Building Products, LTD. www.icfbp.com,
and Vinyl Technologies, Inc.: www.vbuck.com.
Window and door openings require that concrete steel
reinforced lintels be built to span the openings carrying
the load of floors, roof, and point loads from beams,
girders, and trusses. Care should be taken when sizing,
locating, and installing re-bar during the construction
of lintels. Additionally, placement of concrete must
be consolidated to ensure that the steel reinforcing
bar (re-bar) are fully embedded and that no voids occur
in the concrete. This is especially important in areas
around window and door openings, and in lintels where
the positioning of re-bar may inhibit concrete flow.
For this reason, it is always best not to place any
concrete into lintels until the elevation of the concrete
lift being placed can fill the wall and lintel cavities
at the same time, creating a continuous monolithic pour.
Engineering and architectural
specifications and drawings will determine the size,
grade, and the position of the steel reinforcing bars.
The placement and design of steel reinforcing shall
be in accordance with local standards and regulations,
and in conformance with ACI 318. (back
to top)
Bulkheads
Bulkheads are required to stop concrete at open-ended
walls and need external support to keep them in place.
A bulkhead is made by using a 2 x 12 with temporary
1 x 4 flanges attached vertically to each side and placed
over the end of the wall. Adequate bracing or strapping
must be installed to keep the pressure of the concrete
from pushing the bulkhead out during concrete placement.
If the bulkhead is to be left in place, use a treated
2 x 12. Concrete nails, screws, or bolts should also
be installed to extend into the wall cavity before placing
concrete. Bulkheads and other custom areas may also
need to be secured plumb, in two directions, using braces
with turnbuckles.(back to top)
45-Degree and Other Custom Corners
To miter cut Standard ICF straight forms to make
45-degree and various other acute and obtuse corners
is not difficult. Layout two (2) straight forms with
tongue side up and facing in the same direction. Make
measurements on each form starting from the groove end
but on opposite sides (reversing the cut) creating an
axis that divides each form into two asymmetrical pieces.
Mark the vertical lines on the sides of each form with
a square and make vertical miter cuts with a carpenter's
handsaw down the center of the lines.
Make the miter cut by cutting down through both panels
at the same time. Proceeding slowly and following the
lines on both sides of the form will insure an accurate
miter. When both forms are cut, exchange the pieces
to create a form with two (2) opposing corners with
the same angle. Each corner form should have a tongue
and a groove end and a short and a long leg. Fit pieces
together and glue with foam-compatible contact cement
and/or tape. See: Installation Guide.
All special cut corners will need to have temporary
external wood or metal bracing/supports applied vertically
on both sides of the wall assembly and tied together
through the wall with wall ties made of wire. Miter
cut corners and other custom areas may also need to
be secured plumb, in two directions, using braces with
turnbuckles.(back to top)
Rim Joists and Ledgers
The framing of floors and ceilings are often attached
to rim joists or ledgers. To attach rim joists and ledgers
(joist/ledgers) to the side of an ICF wall, a structural
side attachment is required using a series of anchor
bolts or a ledger connector system. Only when concrete
has had time to cure properly should structural framing
be attached to the joist/ledgers that have been installed
with anchor bolts or ledger connectors.
To use the anchor bolt method, multiple sections of
foam panel will need to be removed from the side of
the wall assembly between the stud wall-tie brackets
and within the area to be covered by the joist/ledger.
The joist/ledger is then secured in place over the series
of openings that have been cut in the side of the wall
assembly by attaching it to the wall surface with course
thread screws to the stud flanges. Holes are then drilled
through the joist/ledger to receive the required size
and spacing of anchor bolts as designated by architectural
and/or engineering design. When concrete is pumped into
the wall cavity it will flow into the open spaces in
the foam panels and surround the ends of the anchor
bolts embedding them securely in concrete.
The ledger connector method is simply done by making
a series of single vertical cuts through the foam panels
in the location where the joist/ledger is to be located
in the wall assembly. The ledger connectors are then
pushed into the cuts and friction fit in place. When
the concrete is pumped into the wall cavity it securely
embeds the ends of the connectors. An ICF Ledger Connector
System manufactured by Simpson Strong-Tie is available
through ICF Building Products, LTD.: www.icfbp.com.(back
to top)
Beam and Girder Pockets
To accommodate for the end of a beam, girder, or truss
that will carry the total loads associated with the
interior structure of the building, a beam packet will
need to be formed in the ICF wall assembly before concrete
is put in place. To do this, a piece of the interior
foam panel and/or parts of stud wall-tie brackets will
need to be removed.
Once removed, the open area will need to be blocked-out
with pieces of wood or a slab of foam inserted into
the wall cavity and secured in place to create a void.
The block-out pieces should be made so they can be easily
removed once the concrete has cured. The bottom of the
block-out should be located at the elevation designated
as the bottom of the beam/girder/truss.
It is important to make these pieces slightly larger
than the beam/girder/truss so the end of these structural
members can be inserted easily and the correct elevation
can be adjusted with non-shrink grout, or wood or metal
shims, when the beam/girder/truss is put in place. It
is also important that there is enough concrete support
under the beam pocket to carry the anticipated total
load. To accomplish this, a larger amount of foam panel
may need to be removed to allow for a concrete corbel
to be formed. Exterior bracing may need to be provided
when forming a beam pocked so as to withstand the pressures
of concrete. (back to top)
Brick Ledge
Forming a brick ledge to use for installing veneer
brick and stone can be accomplished by using a simple
wood or metal form attached to the side of the wall
assembly at any desired elevation. Once the elevation
is established, sections of foam are removed from between
the stud flanges and from between the top and bottom
of the brick ledge form allowing concrete to flow into
the brick ledge form. Re-bar is also required in the
construction the brick ledge.
Engineering and architectural
specifications and drawings will determine the size,
grade, and the position of the steel reinforcing bars.
The placement and design of steel reinforcing shall
be in accordance with local standards and regulations,
and in conformance with ACI 318-95 Building Code Regulations
for Structural Concrete.
Utility, Mechanical, and Service
Penetrations
Openings will need to be provided in walls for all
utilities, mechanical systems, and service entrances.
Such items include, but are not limited to, electrical,
telephone and television cables, water supply pipes,
gas lines, air supply and exhaust pipes, ducts, vents,
sewer drain pipes, beam pockets, and access doors or
panels. Penetrations are made so that the installation
of these essential components can be installed after
the concrete is in place, with less effort and cost.
In addition, penetrations for the installation of a
Heat Recovery Ventilator (HRV), also known as an Air-to-Air
Heat Exchanger, should be considered before concrete
placement as well. See: Important Notice below.
A penetration is easily accomplished by sawing a hole
in the desired location through both panels of the form
to allow for the installation of a sleeve or chase (pipe
or frame) through the wall. The sleeve or chase should
be slightly larger than the actual utility or service
penetration being installed. Large access openings are
made in the same way as window openings.
Foam adhesive can be use to secure sleeves and chases
in place, and to seal around the penetration once it
is installed. It is less costly to plan ahead and imagine
the need and possibility of future or additional openings
for penetrations at this time. Extra or unused holes
can be easily filled and covered over for future use
when needed.
Important notice:
Because new buildings are built far more air-tight than
those built in the past, the need for providing clean,
fresh, unpolluted, and balanced indoor air in buildings
has become very important. The need for improved indoor
air quality in ICF buildings is no different. Most all
new buildings need mechanical ventilation to keep the
air inside fresh and prevent the build -up of indoor
air pollutants such as excess moisture, carbon dioxide,
formaldehyde and various volatile organic compounds
found in building materials, paints, furnishings, cleaning
products and smoke. For these reasons it is important
to consider the installation of a Heat or Energy Recovery Ventilator
(HRV or ERV), also known as an Air-to-Air Heat Exchanger as
part of any Heating, Ventilating and Air Conditioning
(HVAC) system in the building at this time. Consult
with your HVAC contractor or consultant concerning the
need for these mechanical devices and the size and location
of any wall penetrations that it will be required for
their installation.
Ventilation Products available through ICF Building Products, LTD. www.icfbp.com
(back to top) |